18 Hawk Retaining Wall


Turf Care staff, along with an equipment operator from Goodwin Golf Construction started the project to replace the failing wooden retaining wall around the first landing area pond on 18 Hawk. Once the wooden wall is removed, the new rock wall installation will begin. This project will take approximately 2-3 weeks to complete. 


Removing failing wooden retaining wall - 18 Hawk Tuesday April 23 2013

Retaining wall removed - Wednesday April 24th 2013