15 Hawk Green Reconstruction

15 Hawk green was reconstructed in the fall of 2013. The entire project from start to finish took 16 days. Click here to view the construction process from start to finish.


The purpose for rebuilding the green complex was to:
  • increase the size of the green from 3800sqft to 6300sqft
  • soften the severe slopes and contours on the green
  • improve surface drainage
  • improve playability of recovery shots
  • expand the playing corridor with selective tree removal  
The new green will be open late spring of 2014. The determining factor will be weather; if there is a warmer spring that facilitates root growth the green will be open for play sooner, however, if it is a cool spring the green will open later.